79. The first inspection activity on a newly listed dam or a dam newly classified as a high-capacity dam must be conducted not later than 3 months after the date on which the dam’s owner is informed of its entry in the register or the entry of its new classification in the register.
O.C. 300-2002, s. 79; O.C. 989-2023, s. 55.
79. The first dam safety review of an existing dam for which approval was granted under the Watercourses Act (chapter R-13) less than 5 years before the date of coming into force of the Act may be conducted, and the attendant report sent to the Minister, within
(1)  the time limit determined under section 78; or
(2)  the end of the tenth calendar year after the year in which the approval was granted,
whichever occurs later.